Concrete Bag Calculator
Calculate how many 40, 60, 80, or 90 lb bags of premixed concrete you need for a slab, footing, square column, or cylinder. Includes waste, total weight, and optional cost.
Premixed Concrete Bag Yields
| Bag size | Approximate yield | Bags per cubic yard before 10% waste |
|---|---|---|
| 40 lb | 0.30 cu ft | 90 |
| 60 lb | 0.45 cu ft | 60 |
| 80 lb | 0.60 cu ft | 45 |
| 90 lb | 0.675 cu ft | 40 |
Frequently Asked Questions about the Concrete Bag Calculator
How many cubic feet does each bag of premixed concrete yield?
A 40 lb bag yields about 0.30 cubic feet of mixed concrete, a 60 lb bag yields 0.45, an 80 lb bag yields 0.60, and a 90 lb bag yields 0.675. The calculator divides your pour volume by the selected yield, applies your waste percentage, then rounds up to whole bags. Check the yield printed on the product you buy.
Which bag size should I use for my project?
60 lb and 80 lb bags are common for residential pours. Use 40 lb bags when handling weight matters. A 90 lb bag yields more concrete but is harder to move. One cubic yard takes 45 bags of 80 lb mix before waste, so compare ready-mix delivery once your project approaches that size.
Why does the calculator add a waste percentage?
Some concrete spills off the mixer, sticks to tools, or gets thrown away because the mix went off in the wheelbarrow. The default 10% waste catches all of that and the inevitable miscalculation in pour depth. Drop it to 5% for clean, simple slabs or push it to 15% for footings with uneven subgrade or many small pours.
How is the total weight calculated?
The calculator multiplies the final bag count (with waste) by the bag weight, so 62 bags of 80 lb mix come out to 4,960 lb of dry product. That figure helps you plan delivery, decide if a pallet jack or two-person carry is enough, and confirm your truck or trailer can handle the load.
When should I switch from bags to ready-mix concrete?
About 1 cubic yard is the break-even point. At that volume you would need roughly 45 bags of 80 lb mix, which costs about as much as the smallest ready-mix delivery and takes far more time and mixing equipment. Above 2 cubic yards, ready-mix wins on both cost and consistency, since one truck delivers the entire pour in a uniform mix.